C
CB@KeyLogic
We have had considerable difficulty with earned value calculations in MS
Project (both 2002 and 2003).
Adding project updates (Status date, % complete, actual cost) does not
always update BCWS, BCWP and ACWP correctly. Errors are confined to
individual tasks (some are correct, others are not), and cannot be explained.
Does anyone have similar issues? Any suggestions?
Project (both 2002 and 2003).
Adding project updates (Status date, % complete, actual cost) does not
always update BCWS, BCWP and ACWP correctly. Errors are confined to
individual tasks (some are correct, others are not), and cannot be explained.
Does anyone have similar issues? Any suggestions?