jobu9999
I'm scheduling a project with a 7 day/10 hour day shift (0700 to 1730 hours)
and a 7 day/10 hour night shift (1700 to 0330 hours). I'm having a terrible
time doing this. Proj tells me that I'm ending a shift before the start time
of a shift. I tried creating 2 calendars (day and night) - still having the
same issue. I've read help in great detail and can find no guidance for my
dilemma.
PLEASE help!