Calendar icon in indicator field

J

Jim Jacks in VA

If I set up MS schedule tasks without a schedule (none), can I change them to
Standard/w Holidays without the calendar icon showing up in their indicator
field?
 
G

Gérard Ducouret

Hello Jim,
Definitly no... But why is this icon so troublesome ?

Gérard Ducouret
 
J

Jim Jacks in VA

Hi Gérard:
Thanks for your reply. I was hoping to set the default task calendar to
Standard/w Holidays and just display variances from the default, not NONE in
the indicator field. My work-a-round is to set the default resource calendar
to Standard/w Holidays and change the task calendar sparingly.

Jim
 
S

Steve House [MVP]

The Project Calendar is used to schedule tasks by default until a resource
is assigned. When you add the resource to the task, the resource's calendar
takes over the scheduling control. Think about it for a moment - you can't
do the work on a task unless the person doing it is at work - so the
schedule of the task should normally follow the resource's fixed work
schedule. If you edit the Standard calendar to include holidays, or if you
copy the standard calendar to a fresh calendar and add the holidays there,
you can then make the resulting calendar the Project Calendar in the
Project/Project Information menu. You can also make that the base calendar
for the resources, thus causing the individual resource calendars to pick up
all that holiday infomation as well. There's no need to use Task Calendars
at all for most of the tasks - the reason they exist is to allow for those
odd-ball exception conditions where tasks must be driven by something other
than the Project Calendar or the assigned Resource Calendars, and in many -
if not most - projects they are unecessary.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top