Calendars - How to remove or delete them

J

john

Howdy,
I have made a bit of a mess creating and updating calendars to my MS
Project. Now that I understand them better, I'd like to get rid of some. How
do I do that?

What is the difference between modifying one of the base calendars and
creating a new one based on the base calendar?
thanks JE
 
D

DavidC

Hi,

go to 'Tools\Organiser' and select the calendars tab. There you will see
the calendars in your project, and can then delete them. Make sure you don't
try deleting the ones from the Global file, which is often listed as the left
hand side frame. Check the drop down box underneath the list of calendars to
make sure you have the correct list of calendars to modify.

Hope this helps.

Regards

DavidC
 
J

john

You rock, thanks much

DavidC said:
Hi,

go to 'Tools\Organiser' and select the calendars tab. There you will see
the calendars in your project, and can then delete them. Make sure you don't
try deleting the ones from the Global file, which is often listed as the left
hand side frame. Check the drop down box underneath the list of calendars to
make sure you have the correct list of calendars to modify.

Hope this helps.

Regards

DavidC
 