V
Veroniq
Hallo,
this issue is concerning the tracking of task progress in
the PWA. In our company we had reinstalled the Project
Server and after completing this, the old (and preserved)
projects have been saved in the new database. Up to this
everything would work fine but the tracking of task
progress by resources in PWA.
The rows (fields) of their old tasks (that they have been
working on and that have not been completed yet) are grey
and they can not fill in the hours worked. Other task
fields, that have been assigned but had not been filled in
in the past, are white and available for entering the
hours.
The method of tracking is set to "Hours of work done per
day or per week" and the Time Period Settings section to
the "Resources should report their hours worked every
day". The projects have been republished so the method of
tracking could take the effect.
Why then the resources can not fill in the hours worked in
their timesheet view? Please advice. Thank you!
this issue is concerning the tracking of task progress in
the PWA. In our company we had reinstalled the Project
Server and after completing this, the old (and preserved)
projects have been saved in the new database. Up to this
everything would work fine but the tracking of task
progress by resources in PWA.
The rows (fields) of their old tasks (that they have been
working on and that have not been completed yet) are grey
and they can not fill in the hours worked. Other task
fields, that have been assigned but had not been filled in
in the past, are white and available for entering the
hours.
The method of tracking is set to "Hours of work done per
day or per week" and the Time Period Settings section to
the "Resources should report their hours worked every
day". The projects have been republished so the method of
tracking could take the effect.
Why then the resources can not fill in the hours worked in
their timesheet view? Please advice. Thank you!