can i add a graphic for a custom date to gantt chart

N

nico

Hi,

i woulkd like the ganttchart to show a graphic (like milestone/deadline) at
a certain
date within the project to represent a critical date. It also means I can
see if this already happened or not and thus take action.

Is this possible at all as I can't seem to add a custom date field to the
bar styles?

thanks
 
J

Jan De Messemaeker

Hi,

Indeed you don't have access to Datex fields in the Bar Styles definition.
Still you can use Startx and/or Finishx.
HTH
 
N

nico

Hi Jan,

Mmm, should have thought about that but the date-field was a bit to obvious
to ignore.
Thanks.
nico
 
M

Mike Glen

Hi Nico,

Have you tried the Deadline date? Add one to a milestone task via the Task
Information/Advanced tab. It will give you notification if the milestone
goes beyond the Deadline date. See Help for Deadline.


FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
N

nico

Hi glen,

Good idea, but I'm already using a deadline for a date further down the
project and thus this is not possible.
 
M

Mike Glen

There's no restriction to the number of deadlines you use - one per task.


Mike Glen
Project MVP
 