Can I create a project without dates, ie, day 1, day 2 etc?

B

Bill

I want to create a project tht does not include dates but uses business days
instead.That is day1, day2, day3 etc.
I'm using Project 2003. Thanks in advance for any assistance. Bill
 
R

Rod Gill

Every task has to have dates. To be date independent, use only links between
tasks. Set the project start date to be that for any month where Monday is
the 1st of the month. Edit the Gantt Chart's timescale to Day1, Day2 or
Week1, Week2 etc. via Format, Timescale.
 
M

Mike Glen

Hi Bill,

Welcome to this Microsoft Project newsgroup :)

The best that Project can offer is Tools/Options.../Date Format: and select
the format for week numbers.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 