Can I define a Group Resource containing multiple individuals?

L

Lou Feola

Within my Project I have defined a Resource that is really a Group of
individuals. The Resource only reflects 1 person working a 10 hour day. In
reality when estimating the project I calculate this resource as
13 individuals and schedule accordingly. Do I need to define 13 separate
Resources?
Thank You.
Lou
 
J

JulieS

Hi Lou,

In the resource sheet you can set the resources' max. units as 13 or 1300%.
If the 13 individuals are truly interchangeable, you can then assign 100% for
one, 300% for 3 etc.

I hope this helps. Let us know how you get along.

Julie
 