Project 2007 Work Field Formula to Exclude Work Done by Resources Not in a Resource Group

D

DaveMori

I have a workshop task in my project schedule which is worked on b
Resources from my company (Resource Group = VENDOR) and resources in th
client's company (Resource Group = CLIENT).

I need a formula to calculate WORK hours for ONLY the resources i
Resource Group = VENDOR. I want to drop any hours that the CLIEN
spends on the task and only calculate VENDOR hours.

Does anyone have a formula? I am familiar with Project, but have no
used formulas before. Could not find a formula to do this in any of th
other forums on the net..

Thanks

+-------------------------------------------------------------------
|Filename: SAMPLE.jpg
|Download: http://forums.techarena.in/attachment.php?attachmentid=10720
+-------------------------------------------------------------------
 