L
Les Mathisen
I am new to Project and am trying to assign three resources to the same task
and have Project calculate the shortest possible finish date. The problem is
each resource is joining the task at different times. Resource #1 starts
today, resource #2 in two weeks and resource #3 in three weeks and each have
different calendars (different vacation days). Project is deviding the work
evenly between the three resources and freeing each resource as their hours
are completed. This means the task isn't completed until the last resource
has finished their work (which is three weeks after the first person), even
though the other two resources are available to help.
Is there some way, other than manually adjusting the hours assigned to each
resource, to have Project use all three resources on the task and complete it
ASAP?
and have Project calculate the shortest possible finish date. The problem is
each resource is joining the task at different times. Resource #1 starts
today, resource #2 in two weeks and resource #3 in three weeks and each have
different calendars (different vacation days). Project is deviding the work
evenly between the three resources and freeing each resource as their hours
are completed. This means the task isn't completed until the last resource
has finished their work (which is three weeks after the first person), even
though the other two resources are available to help.
Is there some way, other than manually adjusting the hours assigned to each
resource, to have Project use all three resources on the task and complete it
ASAP?