Wizards I need some help!
I have set up some external tasks between 2 projects, one master project one
slave. When I open the master project I am notified of differences made in
the other project and given the option to accept. Before I accept I would
like to see what the before date was i.e. what is the difference. All I am
told is the new/after date. Is there a way to get more detail? i.e. I would
like to know 'hey this is 100 days later!'.
It just seems limited in what it says.
Thanks in advance