id like to level one resource who is way overallocated without leveling the
whole plan, i dont see an option to allow this in leveling. hints please or
should i just do this manually? thanks!
 
D

Dale Howard [MVP]

Rob --

Yes, this is possible. Here's how:

1. Apply the Resource Usage view
2. Select the overallocated resource in question
3. Click Tools - Level Resources
4. Select the leveling options you want to use with this resource
5. Click the Level Now button
6. In the Level Now dialog, select the "Selected resources" option and
click OK
7. Apply the Leveling Gantt view to see the results (click View - More
Views - Leveling Gantt)

Hope this helps.
 
R

Rob

thanks, worked great.
Rob --

Yes, this is possible. Here's how:

1. Apply the Resource Usage view
2. Select the overallocated resource in question
3. Click Tools - Level Resources
4. Select the leveling options you want to use with this resource
5. Click the Level Now button
6. In the Level Now dialog, select the "Selected resources" option
and click OK
7. Apply the Leveling Gantt view to see the results (click View -
More Views - Leveling Gantt)

Hope this helps.
 