Can I specify a date variable in a Project View?

C

cornasdf

Hey all,
I need to create a new view that only shows the next 21 days of project
tasks. I can define this statically under the 'manage views' section. ie, i
can create a filter that says 3/15/09 or similar and it seems to give me what
I am looking for. Is there any way to make this dynamic? In, say, TFS, I
would put @Today + 21. Does project server have anything similar?

Thanks
ej
 
D

Dale Howard [MVP]

ej --

There is no way to create a dynamic PWA view the way you wish to do. Sorry.
 
C

Christophe Fiessinger [MSFT]

yes this would require a custom SQL Server Reporting Services report for
instance
 
C

cornasdf

slumming... what about using a scripting language to update the views. is
there any guidance on using (hopefully) powershell to interact w/ project
server views?

Thanks
ej
 