B
Brian
The assignment of additional resources to a task forces the baseline of the
work at the task level to track earned value and variances. Work already
performed by another resource assigned to the same task is also changed by
the baselining of the task. This loses the earned value/variance information
for the legacy resource.
Is there a method in MS Project 2003 to baseline per resource instead of
task? Or, is there a work around?
work at the task level to track earned value and variances. Work already
performed by another resource assigned to the same task is also changed by
the baselining of the task. This loses the earned value/variance information
for the legacy resource.
Is there a method in MS Project 2003 to baseline per resource instead of
task? Or, is there a work around?