D
Dmatzy
I am using the default resource usage view and find it very helpful.
However, I noticed that I cannot find 'work remaining' in the list of fields
available to show as a time-phased field.
Is this available in some way? If not, is there a reason why? This would
be very helpful to have in the resource usage view. I could use that field
in this view to know how much remaining time I need from each person on the
plan by week and by month.
Now, the only remaining field I can get is 'remaining availability', which
is does not answer my question.
However, I noticed that I cannot find 'work remaining' in the list of fields
available to show as a time-phased field.
Is this available in some way? If not, is there a reason why? This would
be very helpful to have in the resource usage view. I could use that field
in this view to know how much remaining time I need from each person on the
plan by week and by month.
Now, the only remaining field I can get is 'remaining availability', which
is does not answer my question.