Hi Guys,
Newbie here. I'm trying to create a task using Project Web Access but I
want it to be a subtask of the task I was assigned. In the question "What
outline level do you want to create the new task in", the option to make the
new task a subtask of, is grayed out. How can I enable that option? I have
administrator permissions for the server.

TIA, Gus
 
D

Dale Howard [MVP]

Gus --

Are there summary tasks in the project that represent things like Phases and
Deliverables? If not, the option is grayed out, as you can only make the
new task a subtask of an existing summary task. Hope this helps.
 