W
woodsy
Just started with Project 2007 last week and I already have an issue! Let's
say I create a task, then put some subtasks under it (indented). If I put in
a duration for one of the subtasks at 5 days, the blue bar for the subtask
extends 5 days, but the main task stays at the default 1 day. It doesn't
matter if I open a new project, open a project someone else sends me, etc.,
same thing happens. However, if I send my Project to someone else,
everything looks as it should. I assume I have some kind of formatting or
filtering issue, but I'm not experienced enough in project to identify it.
Any help would be appreciated! Thanks.
say I create a task, then put some subtasks under it (indented). If I put in
a duration for one of the subtasks at 5 days, the blue bar for the subtask
extends 5 days, but the main task stays at the default 1 day. It doesn't
matter if I open a new project, open a project someone else sends me, etc.,
same thing happens. However, if I send my Project to someone else,
everything looks as it should. I assume I have some kind of formatting or
filtering issue, but I'm not experienced enough in project to identify it.
Any help would be appreciated! Thanks.