Newbie- Subtask duration not driving main task duration

W

woodsy

Just started with Project 2007 last week and I already have an issue! Let's
say I create a task, then put some subtasks under it (indented). If I put in
a duration for one of the subtasks at 5 days, the blue bar for the subtask
extends 5 days, but the main task stays at the default 1 day. It doesn't
matter if I open a new project, open a project someone else sends me, etc.,
same thing happens. However, if I send my Project to someone else,
everything looks as it should. I assume I have some kind of formatting or
filtering issue, but I'm not experienced enough in project to identify it.
Any help would be appreciated! Thanks.
 
J

Jim Aksel

Might you have calculations set to manual?
Press F9, if this fixes the problem, then you are set to manual.

Change to automatic: Tools/Options/Calculation (tab) and set to automatic.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 