Q
quixote
I am getting frustrated with how Project calculates(or doesn't)...I know this
is probably user error.
I have added tasks, indented some lines so they would be subtasks, assigned
a resource and added work hours. The subtask work hours are not adding up to
the main task..the task just has zero even though subtasks have values and
duration hasn't changed from the default.
Another issue...I have the start date from the past but some of the subtasks
have the current date and I can't change it...what am I doing wrong??!!!
also...I played around with trying to set up a 24/7 calendar but it didn't
seem to work. I have an iterative project that should have lots of
predecessors that will just continue on regardless of the time of day or what
day it is...but I can't make sense of how duration is being calculated...any
ideas on this would be appreciated too
Thanks
is probably user error.
I have added tasks, indented some lines so they would be subtasks, assigned
a resource and added work hours. The subtask work hours are not adding up to
the main task..the task just has zero even though subtasks have values and
duration hasn't changed from the default.
Another issue...I have the start date from the past but some of the subtasks
have the current date and I can't change it...what am I doing wrong??!!!
also...I played around with trying to set up a 24/7 calendar but it didn't
seem to work. I have an iterative project that should have lots of
predecessors that will just continue on regardless of the time of day or what
day it is...but I can't make sense of how duration is being calculated...any
ideas on this would be appreciated too
Thanks