Can't change my first estimated duration/date in Project

R

R

Sorry - 1st time user. I entered my lists of tasks in project, but am having
trouble going back to change the duration and start dates for both individual
tasks and phases i have created. Any solutions are appreciated.
 
G

Gérard Ducouret

Hello R,
You can't change the Duration of Summary tasks because it is calculated by
Project.
Don't enter dates in the Start and Finish fields. Enter relationships in the
Predecessors column.

Gérard Ducouret
 
M

Mike Glen

Hi R,

Welcome to this Microsoft Project newsgroup :)

If you are a new user, you might like to have a look at my series on
Microsoft Project in the TechTrax ezine, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top