E
Erik Vetters
Hi Project,
I have the following scenario.
A MS Project 2003 is saved over ODBC to an MS SQL Server.
I'm want to manipulate only the Work and Duration and Assignments
directly in the Database via a simple Webinterface.
I have used this Guide / Whitepaper http://www.msproject.com/P2K Projdb.htm
very
on how to do that.
No my problem:
If I change Durations and or Work in my Webinterface and open the
Project File later via ODBC the Values Date Start and Date doesn't
gets recalculated based on the Work and Duration.
Of course I'm able to change End-Date too, but then I have to
recalculate "all" Tasks based on the newly added
values.
Is there a way in Project so that I can say Recalculate everything and
based on Work and Duration and don't change them.
Hope somebody can help me and understand what I mean.
Many Greetings
Erik
P.S.
By the way, does someone have done such things before. I have seen
some thing on the Web but not so detailed stuff.
I have the following scenario.
A MS Project 2003 is saved over ODBC to an MS SQL Server.
I'm want to manipulate only the Work and Duration and Assignments
directly in the Database via a simple Webinterface.
I have used this Guide / Whitepaper http://www.msproject.com/P2K Projdb.htm
very
on how to do that.
No my problem:
If I change Durations and or Work in my Webinterface and open the
Project File later via ODBC the Values Date Start and Date doesn't
gets recalculated based on the Work and Duration.
Of course I'm able to change End-Date too, but then I have to
recalculate "all" Tasks based on the newly added
values.
Is there a way in Project so that I can say Recalculate everything and
based on Work and Duration and don't change them.
Hope somebody can help me and understand what I mean.
Many Greetings
Erik
P.S.
By the way, does someone have done such things before. I have seen
some thing on the Web but not so detailed stuff.