can't indent/outdent or show/hide subtasks

4

4lane

Hi -

I have project file that has inactive indent/outdent and show/hide subtasks
buttons. I can't do either. If you try to cliick on the little '+' to show
subtasks it won't do anything. same goes for indent/outdent. any ideas,
please?? thx!!

r
 
J

Joao Bras - Brasmatica

Hi again,

You have to select the task before you try to outdent ou ident them, if not
it appear grey. It's the only thing I remember. If it doesn't work, you can
send the project (if you want and it's possible) so I can see the problem.

Joao
 
4

4lane

I don't think this is the problem. I'm using Project 2000. And, you can't
indent/outdent ANYTHING. Nor can you show/hide any tasks. I've used this for
a year now with no problems. so, i don't think this is the solution
unfortunately....
 
J

John

r,
Is it possible you have either a filter applied or the file is sorted?
These are common scenarios that are often overlooked when indent/outdent
are strangely inactive.

Hope this helps.
John
 
4

4lane

Exactly, but when you select a task, all those buttons remain greyed out,
when they would normally become active. therefore, you can't use them.
how/where can i send you this as an example?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top