indent, outdent is faded

M

Majid

Hello Dear,
In one of my project file, the indent and outdent is faded
and I am not able to create subtask.
Let me explain what problem I recentely had. I have an
error message each time I am creating a new project and
stating that "the veiw or report cannot be displayed
because the table "entry" on which it is based has been
deleted" I have created the Gantt view from view menu
already and it is okay.
Please advise
Regards, Majid
 
M

Majid

Thank you Jan it did work.
Would you please advise why each time I create a new
problem I am getting the error message as I have explained
in my previous posting. Even When I set it up agian I
have to repeat it for the new projects.
Regards,
Majid
 
J

Jan De Messemaeker

Hi Majid,

This means that the table "Entry" no longer exists in your Global.mpt file
Open a file that works (close all the others to simplify)
Tools, Organizer, Tables, select "Entry" on the side of the open Project
Copy to Global.mpt
HTH
 
M

Majid

Thank you Jan it did work
-----Original Message-----
Hi Majid,

This means that the table "Entry" no longer exists in your Global.mpt file
Open a file that works (close all the others to simplify)
Tools, Organizer, Tables, select "Entry" on the side of the open Project
Copy to Global.mpt
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
"Majid" <[email protected]> schreef in bericht


.
 