John,
I did respond to his question in another new message on 4/12. I hit
the new
button instead if the reply one. So sorry, my error. Please see below:
"Somewhat, but each file is different as far as how far out they are
extended.
ie: 2006, long range (out to 2010) which includes 2006, east west
combined
(for 2006-2007, heavy workload , overlapping etc. Each file is
reviewed by
different people and I just want to make it easier on myself."
This may seem silly to you but my boss wishes it done this way. He
likes the
product . As I said, I was only trying to make it a bit easier on
myself. I
will see if I can get help elsewhere. Sorry to have bothered you.
Have A Good Day,
Vicky
:
I have never received an answer. Is there a way to do this?
Vicky,
You never received an answer because what you are asking quite
frankly
doesn't make a whole lot of sense. That's how Steve saw it and asked
his
question but you never answered it. I have the same question as Steve
plus a few other observations.
When you say you, "...only maintain the start [and] finish dates...",
what exactly do you mean? On the surface it sounds like you are
manually
entering dates into the task Start and Finish fields. If so, you are
basically preventing Project from doing what it is designed to do,
that
is, to help you manage your project by automatically calculating the
schedule based on estimated duration and links between tasks. If you
want to put dates in manually, you might as well use Excel, it would
be
a whole lot easier.
You also mention that you somehow want to edit one file and have the
other four respond in kind. That will only happen if the tasks in
each
file are replicated (as Steve asked) or if the tasks are linked.
We can give you some help if you tell us what you really have and
what
your end goal is.
John
Project MVP
:
Are you saying the same tasks are in all 5 files, in other words,
there are
5 independent copies of the same project plan????
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
I maintain 5 project files. I only maintain the start finish
dates and the
tasks. I am not concerned with % or constraints, etc. Is there
a way to
change dates and/or tasks in 1 file and have the information
filter to the
other 4 files so that I do not have to go in to each file and
change the
information?