Change print display dates for a gantt chart

S

sjohnson

I am using microsoft project 2003 and I used an old schedule for a template.
I adjusted all the gantt dates for the project and I can see it on the
screen, but when I do a print preview the gantt chart is still displaying the
timefield from the template I used and nothing is displayed in the chart area.

Help
Shelby k. Johnson
 
J

JulieS

Hello Shelby,

Did you adjust the start date of the project through Project > Project
Information?

As a short-term fix, you can adjust the dates printed in the File >
Print dialog box.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"(e-mail address removed)"
 