change recurring task symbols

G

graphx

I am trying to change the milestone "triangles" my recurring task to a "Bar".
I inherited this file and this has made it difficult. I don't really
understand the bar styles definition dialog box and I think this is where I'm
hosed. When I put in 100% the symbol on the rollup disappears even though I
have the box checked. I only want to see the rollup. Does anyone know what
I'm doing wrong?
 
M

Mike Glen

Hi graphx ,

Welcome to this Microsoft Project newsgroup :)

Firstly, I suggest you make the recurring task into a task by giving it a
duration, which will then show the bars.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

wrote:
 
S

Steve House [Project MVP]

If your recurring task has a duration it will be a bar. A milestone has no
duration and thus is simply a point on the calendar - bars extend from point
"A" to point "B" - with no duration there's no "A" and "B" to draw the bar
between. If you specify each occurance of the task to have zero duration
when you create it, you get a string of diamonds. If you say it has a
duration, say 1 hour set aside for a meeting every Friday afternoon, then it
will show up as a string of bars.
 