That's not the way it works on my copy of P2003. All settings
out-of-the-box default everything, fixed unit tasks, standard calendar.
Create task Fidget starting Monday with 5 days duration. Create 2
resources, Fred and Ethyl. Assign Fred to the task 100%. Task usage view
shows Fred scheduled 8 hours per day for 5 days for 40 total hours. Now
mark the task 40% complete. Display actual work, shows Fred actual work 8
hours per day Mon and Tue, still scheduled 8 hours per day Wed Thur Fri.
Now switch to Gantt chart and use the taskbar button to display the Task
Assignment window. Select Fred, click Replace, and select Ethyl. Now the
assignment window shows them both on the task 100% BUT the duration has not
changed. Switch over to task usage view again. It now shows Fred's work at
a total of 16 hours for both scheduled work and actual work, 8 hours each
per day on Mon and Tue. But now there's nothing in scheduled work for him
for the rest of the week. Instead, Ethyl shows blank on Mon and Tue but
picking up on Wed Thur, and Fri shows her scheduled for 8 hours per day, a
total of 24 hours to her.
--
Steve House [MVP]
MS Project Trainer/Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs