K
KevDev
I have a task that requires two resources to work concurrently. It is
series of presentations that need to occur within a single span of fiv
days. Both resources must be available to attend each and ever
presentation within that 5 day period.
There is work that must be complete prior to presentations, therefor
this task has a predecessor. It so happens that one of the resource
that must perform the task is away on vacation when the predecesso
finishes. Even though the vacation is entered as an exception in th
calendar of the resource, MS Project still schedules the presentatio
task to start right after the predecessor completes, when only one o
the resources is available.
What do I need to do to have the task scheduled asap, but only when bot
resources are available
series of presentations that need to occur within a single span of fiv
days. Both resources must be available to attend each and ever
presentation within that 5 day period.
There is work that must be complete prior to presentations, therefor
this task has a predecessor. It so happens that one of the resource
that must perform the task is away on vacation when the predecesso
finishes. Even though the vacation is entered as an exception in th
calendar of the resource, MS Project still schedules the presentatio
task to start right after the predecessor completes, when only one o
the resources is available.
What do I need to do to have the task scheduled asap, but only when bot
resources are available