R
Rocker
Hello,
I created and saved a simple project file in Microsoft Project 2003 in which
all tasks are fixed duration and effort driven. When I reopened the project
file, all tasks are still fixed duration but now they are not effort driven
and all of the Work values have automatically changed to zero. What can I do
to disable these changes that happen automatically when I reopen the project
file?
Thanks,
Rocker
I created and saved a simple project file in Microsoft Project 2003 in which
all tasks are fixed duration and effort driven. When I reopened the project
file, all tasks are still fixed duration but now they are not effort driven
and all of the Work values have automatically changed to zero. What can I do
to disable these changes that happen automatically when I reopen the project
file?
Thanks,
Rocker