In my MS Project 2007 I cannot change working time in calenders.
The 'buttons' that I used in 2003 do not work, and the tabs referred to in
HELP do not exist.
 
D

Dale Howard [MVP]

bradc --

It sounds like you are using Microsoft Project 2007 with Project Server
2007. If this is the case, you cannot create or edit base calendars.
Instead, only the Project Server administrator can do this. If you ARE
using Project Server 2007, then in the future please post your Project
Server questions in the microsoft.public.project.server newsgroup, as this
newsgroup is dedicated to the Microsoft Project desktop application only.
Hope this helps.
 