Changing Days to Hours

J

John

I am working on a project that takes place over the course of a 48 hour
period. I'd like to set up the project so it calculates the summary
tasks and project summary task into hours.

Does anyone know how to make the needed changes to do this?
 
G

Gérard Ducouret

John,

Tools / Options / Schedule / Duration is entered in... Hours

Hope this helps,

Gérard Ducouret
 