T
tshad
In Project 2003, I have a project I created and have 3 resources.
In the duration of a task I have set it as 4 days.
For my resources:
Developers 200% Max Units ( I assume this means equivalent to 2
developers)
Developer1 100% Max Units
Developer2 100% Max Units
When I assigned "Developers" to the task, the Duration didn't change. If I
change the Max Units of "Developers" to 400%, the tasks Durations still
doesn't change.
But if I add Developer1 to the resource (Developers,Developer1), the tasks
Duration changes to 2 Days (and the ending date changes as expected).
If I now add Developer2 to the task (Developers,Developer1,Develop2), the
duration changes to 1.33 Days (with the ending date changing as expected).
If I double click on the task, it shows all 3 tasks as 100% as if they are
equivalent. But isn't "Developers" the equivalent of 4 people?
Thanks,
Tom
In the duration of a task I have set it as 4 days.
For my resources:
Developers 200% Max Units ( I assume this means equivalent to 2
developers)
Developer1 100% Max Units
Developer2 100% Max Units
When I assigned "Developers" to the task, the Duration didn't change. If I
change the Max Units of "Developers" to 400%, the tasks Durations still
doesn't change.
But if I add Developer1 to the resource (Developers,Developer1), the tasks
Duration changes to 2 Days (and the ending date changes as expected).
If I now add Developer2 to the task (Developers,Developer1,Develop2), the
duration changes to 1.33 Days (with the ending date changing as expected).
If I double click on the task, it shows all 3 tasks as 100% as if they are
equivalent. But isn't "Developers" the equivalent of 4 people?
Thanks,
Tom