R
Refreshing
Hello, I'm Refreshing.. and it's been a very very long time since I've use
Project and I've forgotten how to use the product. I inherited a 7000 line
file that was created by someone who is no longer here. I recently had to
change about 700 task in the file in which I did by cutting and pasting. I
then went back and reset the predecessors starting at the top with Phase I.
Some of them changed, but not all. Now here's the problem I need to change
many of the dates starts and finishes, but project is not allowing it.
All but a few task have a contraint type of ASAP, I have a few with SNET and
I using two calendars. When I try to set the dates all of the dates start to
move.
Project and I've forgotten how to use the product. I inherited a 7000 line
file that was created by someone who is no longer here. I recently had to
change about 700 task in the file in which I did by cutting and pasting. I
then went back and reset the predecessors starting at the top with Phase I.
Some of them changed, but not all. Now here's the problem I need to change
many of the dates starts and finishes, but project is not allowing it.
All but a few task have a contraint type of ASAP, I have a few with SNET and
I using two calendars. When I try to set the dates all of the dates start to
move.