C
Cecilia
Hi,
I am creating a timeline using Microsoft Project 2000. I have two tasks on
my timeline and I want "Task #2" to start 200 days after "Task 1". I
double-clicked on "Task 2" and selected the "Predecessors" tab, I picked
"Task 1" to be the predecessor and input a lag of 200 days. It seems that the
program is only counting "business days" because the date it assigns to Task
2 is far beyond the 200 days. I want weekends to be counted in the 200 days.
How do I fix this?
Thanks!
I am creating a timeline using Microsoft Project 2000. I have two tasks on
my timeline and I want "Task #2" to start 200 days after "Task 1". I
double-clicked on "Task 2" and selected the "Predecessors" tab, I picked
"Task 1" to be the predecessor and input a lag of 200 days. It seems that the
program is only counting "business days" because the date it assigns to Task
2 is far beyond the 200 days. I want weekends to be counted in the 200 days.
How do I fix this?
Thanks!