L
L Kelly
Question regarding MS Project Timeline:
My company recently changed to an accounting system where
each month ends on the 4th Sunday of each month as opposed
to the last friday of the month. As far as I know, MS
Project only deals with actual calendar months.
Example - schedule is baselined as normal (so Jan 31 is
the end of the calendar month in Project). January 2004
accounting-wise really ends on Jan 25, 2004. So the week
of Jan 26-30 is really in the accounting month of
February. So any work not completed by Jan 25 has to be
moved to start after Jan 31. This causes a week schedule
slip compared to the baseline which finishes Jan 31. We
have had to go back and readjust the baseline spread to
move this week of baseline into February to avoid charging
the program an unfair week's slip of the schedule for any
of those tasks. We now have to do this every month where
the 4th Sunday of the month is not the end of the month or
when it's the end of the quarter.
We were afraid this is the only way to fix this when
establishing the baseline but does anyone know a way to
change MS Project calendar to match an accounting calendar
(that's different from the real calendar) like this
without having to set the task dates in the next month?
Back to my example - I don't want the tasks for Jan 26-30
to have to be set in actual month of February when I
baseline because that doesn't help the project team manage
their schedule correctly. They will be doing the work the
week of Jan 26-30 and schedule dependencies need to be set
correctly based on the actual dates.
Any insight would be most helpful! THANKS!
My company recently changed to an accounting system where
each month ends on the 4th Sunday of each month as opposed
to the last friday of the month. As far as I know, MS
Project only deals with actual calendar months.
Example - schedule is baselined as normal (so Jan 31 is
the end of the calendar month in Project). January 2004
accounting-wise really ends on Jan 25, 2004. So the week
of Jan 26-30 is really in the accounting month of
February. So any work not completed by Jan 25 has to be
moved to start after Jan 31. This causes a week schedule
slip compared to the baseline which finishes Jan 31. We
have had to go back and readjust the baseline spread to
move this week of baseline into February to avoid charging
the program an unfair week's slip of the schedule for any
of those tasks. We now have to do this every month where
the 4th Sunday of the month is not the end of the month or
when it's the end of the quarter.
We were afraid this is the only way to fix this when
establishing the baseline but does anyone know a way to
change MS Project calendar to match an accounting calendar
(that's different from the real calendar) like this
without having to set the task dates in the next month?
Back to my example - I don't want the tasks for Jan 26-30
to have to be set in actual month of February when I
baseline because that doesn't help the project team manage
their schedule correctly. They will be doing the work the
week of Jan 26-30 and schedule dependencies need to be set
correctly based on the actual dates.
Any insight would be most helpful! THANKS!