K
Kishore
We are using Project Server 2003. When we are trying to open a project,
Project Professional says, it has a circular relationship on task 457..., and
unable to calculate. So, I did following:
1) Tried to find circular links in MSP_LINKS table...couldnt figure out, so
1) Deleted All links on Summary Tasks from MSP_LINKS table --- still same
issue
2) Delete all other links on that project -- still same issue
This project is a stand alone project, not a master project, not a sub
project, no cross project links.
Thanks in advance for all help.
Project Professional says, it has a circular relationship on task 457..., and
unable to calculate. So, I did following:
1) Tried to find circular links in MSP_LINKS table...couldnt figure out, so
1) Deleted All links on Summary Tasks from MSP_LINKS table --- still same
issue
2) Delete all other links on that project -- still same issue
This project is a stand alone project, not a master project, not a sub
project, no cross project links.
Thanks in advance for all help.