Clear leveling not clearing everything

S

susiew32

Hi guys,

If I level the resources in my project, some of the dates move around. Then
I clear the leveling for the whole project, but when I look at the Leveling
Gantt, the blue bars reflect the current start dates, and the green bars are
pushed beyond the original start date.

Help! Thanks.
 
J

Jan De Messemaeker

Hi,

The bars in the leveling Gantt use Preleveled Start.
At each leveling or clearing action, whatever value is in Start is copied
into preleveled start.
For instance when you push level now twice without any changes, preleveled
start will simply be equal to Start and the leveling Gantt will shownothing.

So it's the graphics that are questionable: CLEAR LEVELING DEFINITELY UNDOES
ALL LMEVELING DELAYS!

Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top