In an old post about resource leveling I saw the following sentence:
"To level one resource at a time, you must deselect the "Clear
leveling values before leveling" option in the Resource Leveling
dialog".
What is the logic behind this? and why only for "one resource at a
time" leveling and not "All together" leveling?

One more question on this subject, if I may:
Why these two scenarios do not give the same result, and when should I
use which method:
1) Click "Level Now" when "Clear leveling values before leveling"
check-box is checked
2) Click "Clear Leveling" button (at the bottom of the dialog box) and
then click "Level Now"

Thanks for the help..
Gil
 
J

JulieS

Hello Gil,

I don't agree with the comment that Clear leveling values before
leveling has anything to do with leveling one resource at a time. To
level only one resource at a time, make sure you use the Resource
Leveling command from a resource view (Resource Usage for example)
instead of a task view (Gantt chart for example.) If you level with a
Resource view active, you'll get the option to level the entire list
of resources or just the selected resource.

The button Clear leveling is only available if you are in a task view.
So if you are leveling from a resource view, the option "Clear
leveling values before leveling" will remove leveling from tasks the
selected resource is assigned to.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project

"Gil" wrote in message
news:f0ea81b5-7f16-48b0-ab2a-5f3d56c702ff@l64g2000hse.googlegroups.com...
 
G

Gil

Hello Gil,

I don't agree with the comment that Clear leveling values before
leveling has anything to do with leveling one resource at a time.  To
level only one resource at a time, make sure you use the Resource
Leveling command from a resource view (Resource Usage for example)
instead of a task view (Gantt chart for example.)  If you level with a
Resource view active, you'll get the option to level the entire list
of resources or just the selected resource.

The button Clear leveling is only available if you are in a task view.
So if you are leveling from a resource view, the option "Clear
leveling values before leveling" will remove leveling from tasks the
selected resource is assigned to.

I hope this helps.  Let us know how you get along.

Julie
Project MVP

Visithttp://project.mvps.org/for the FAQs and additional information
about Microsoft Project

"Gil"  wrote in message







- Show quoted text -

Juie, Thanks so much for the help. I will repeat my second question:
How come the result I get after leveling with the "clear leveing
values" checked is different from the result I get after clicking the
"Clear leveling" and then clicking "Level now"? both actions are taken
from a Task view... Will "clear leveling values" clears leveling
values ONLY from tasks that are about to be leveled again??
Thanks,
Gil
 
J

JulieS

:
Juie, Thanks so much for the help. I will repeat my second question:
How come the result I get after leveling with the "clear leveing
values" checked is different from the result I get after clicking the
"Clear leveling" and then clicking "Level now"? both actions are taken
from a Task view... Will "clear leveling values" clears leveling
values ONLY from tasks that are about to be leveled again??
Thanks,
Gil
Hi Gil,

It's tough for me to explain why things are different without seeing your
project file specifically. Try switching to the Leveling Gantt View and
experiment with both options. I believe the "Clear Leveling" button removes
leveling delay plus splits from all tasks. When you click the Clear leveling
button, I assume you are clearing leveling from all tasks?

You might also like to add the field preleved start or preleved finish to
see what project is doing a bit more clearly. I find that if I do not use
the "Clear leveling button" and re-leveling a project the preleved start
field changes on the second pass -- even if no additional leveling has been
done.

I hope this helps.

Julie
 
G

Gil

:

<snip>




Hi Gil,

It's tough for me to explain why things are different without seeing your
project file specifically.  Try switching to the Leveling Gantt View and
experiment with both options.  I believe the "Clear Leveling" button removes
leveling delay plus splits from all tasks.  When you click the Clear leveling
button, I assume you are clearing leveling from all tasks?

You might also like to add the field preleved start or preleved finish to
see what project is doing a bit more clearly.  I find that if I do not use
the "Clear leveling button" and re-leveling a project the preleved start
field changes on the second pass -- even if no additional leveling has been
done.

I hope this helps.

Julie

Julie,
Thanks again, I will try your suggestion.
Gil.
 
J

JulieS

"Gil" wrote in message
:

<snip>




Hi Gil,

It's tough for me to explain why things are different without seeing
your
project file specifically. Try switching to the Leveling Gantt View
and
experiment with both options. I believe the "Clear Leveling" button
removes
leveling delay plus splits from all tasks. When you click the Clear
leveling
button, I assume you are clearing leveling from all tasks?

You might also like to add the field preleved start or preleved
finish to
see what project is doing a bit more clearly. I find that if I do
not use
the "Clear leveling button" and re-leveling a project the preleved
start
field changes on the second pass -- even if no additional leveling
has been
done.

I hope this helps.

Julie
Julie,
Thanks again, I will try your suggestion.
Gil.

You're most welcome Gil. Do post again should you have any further
questions. Good luck.
Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top