Stefan Hovens
Dear reader,
When I use resource leveling by default the box: "Level only within
available slack" is disabled. In this way you can get better leveling, in
theory even a 100%.
I suppose the more delay MS is putting on the total project duration, the
better the leveling will be until a maximum.
As a project manager you would like to see what a delay will do with your
leveling. So you would like to be able to have a graphs that sets out the
leveling against te total delay of the project. I suppose MP chooses
automaticly a value that is on this graph.
Can you make such a graph quickly?
How does MP determens this value?
All answers and quistons are welcome.
Greetings,
Stefan Hovens
When I use resource leveling by default the box: "Level only within
available slack" is disabled. In this way you can get better leveling, in
theory even a 100%.
I suppose the more delay MS is putting on the total project duration, the
better the leveling will be until a maximum.
As a project manager you would like to see what a delay will do with your
leveling. So you would like to be able to have a graphs that sets out the
leveling against te total delay of the project. I suppose MP chooses
automaticly a value that is on this graph.
Can you make such a graph quickly?
How does MP determens this value?
All answers and quistons are welcome.
Greetings,
Stefan Hovens