A few things may help.
First, use the Status Column. Although it will not give you a %Complete, it
will give you "Late", "On Schedule" or "Future Task". A task is on schedule
if the %Complete line on the Gantt Chart passes through 12:01 AM on the day
before the status date, tasks that are ahead of schedule are listed as on
schedule.
Second, add a progress line (Tools/Tracking/Progress Line...) and show it at
the status date. If the line shows snaking to the left of the status date
those items are behind. Snaking to the right shows ahead of schedule. The
ideal case is a nice vertical line....
A third choice is a Grid Line (Format/Gridlines...). This allows you to
display a vertical line through the status date. Use your eyes to visually
inspect progress lines that should be touching up to this line. We use this
in conjunction with the status column.
Those are your best options. Now to answer your question. You need to copy
your %Complete (actual) over to a spare column such as Text1 so it can be
saved. Then, Tools./Tracking/Update Project and select the top choice and
"entire project" at the bottom. The date picker will default to the status
date - change it if you want to. This will display the desired %Complete,
but you just changed all your %Completes to incorrect values. So, you can
copy those values over to a second spare text column (Text2)... then make
sure to copy your original %complete back from Text1 into the %Complete
column.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project