Common Resource Pool : Modifying Calendar to reflect vacation

S

spi

Hi,

I noticed if I update resource calendar (of a resource in resource pool) to
reflect vacation, the changes are not getting saved. If I reopen the project
(associated with common resource pool file) it shows resource is available
during his/her vacation.

Has anyone faced same issue before? If yes, how did you resolve?

Would appreciate any pointers.

Thanks!
 
J

JulieS

Hi spi,

When you attached the sharer file to the pool (Tools > Resource Sharing
Share Resources) did you select the option for pool takes precedence
on conflict with calendar or resource information? If you did, you will
need to open the pool file with write access to make the change.

I hope this helps. Let us know how you get along.

Julie
 
S

spi

Hi Julie,

Thanks! Apologies for the delay in the response. We resolved the issue by
directly modifying the resource file to document the vacation, i.e. by
opening resource sheet as a project plan and changing the working time
appropriately.

btw, we used the option of 'pool takes precedence' and ensured resource file
is opened with read/write privilege. Somehow, it didn't work by updating
resource sheet associated to project. May be a caching issue.

Cheers!
 
J

JulieS

You are most welcome SPI and thanks for the feedback. Glad to know you
got it sorted out.

Julie
 