S
spi
Hi,
I noticed if I update resource calendar (of a resource in resource pool) to
reflect vacation, the changes are not getting saved. If I reopen the project
(associated with common resource pool file) it shows resource is available
during his/her vacation.
Has anyone faced same issue before? If yes, how did you resolve?
Would appreciate any pointers.
Thanks!
I noticed if I update resource calendar (of a resource in resource pool) to
reflect vacation, the changes are not getting saved. If I reopen the project
(associated with common resource pool file) it shows resource is available
during his/her vacation.
Has anyone faced same issue before? If yes, how did you resolve?
Would appreciate any pointers.
Thanks!