Completed tasks in status report

S

serverterri

Hi there,
I'm trying to put together a status report that I would like to send out to
all team members. I would like it to include the completed tasks for the
week. Isn't there a way to have Server show this information for them? We
are using project server 2007.

Thank you
 
M

Marc Soester [MVP]

Hi serverterri,

the functionality you are asking for does not come out of the box. You may
want to think about creating a report using reporting service which will
allow you to create a "completed task report" which team members can then
print out.

You could also use the Project Details ( by drilling down to the Project in
PWA) to create a view which only displays completed task for a project.

Hope this helps
 