Completing a task with zero actuals

G

Guest

I would make sure that you are marking % Work complete
and not just % complete. You shouldn't get the error if
you do that with it all at 0. If you leave the 20 hours
originally assigned in the work column and then mark it
complete it will force actual work to changed to assigned
work. I don't know of anyway to keep those hours and mark
it complete.

-----Original Message-----
Hi,

Iâ?Tm having a problem using managed time sheets. I
created a task and baselined it for 20 hours. It turns
out we didnâ?Tt need to complete the task, so the
resource zeroed out remaining work and updated it. Now
that Iâ?Tve accepted the update, the task has zero work,
zero actual work, zero remaining and zero percent
complete.
The problem with this is that BCWP is also zero. I
would like BCWP to reflect the 20 hours originally
scheduled. If I manually set percent complete to 100% I
get a warning that actuals will become out of sync with
protect actuals, and if I sync back to protected actuals,
it sets percent complete back to 0%. Any ideas for a way
to work around this? Iâ?Td rather not enter a token hour
to complete the task as that will reduce the accuracy of
other tasks.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top