How can I Link the completion date of a task to coincide with the completion
date of another task?
 
M

MT_PMP

WSB,

Try setting the "Finish-to-Finish" constraint on the relationship between
the two tasks. This will require that in order for the linked task to
finish, it's predecessor must finish.

Go to the Task Information view by double-clicking on the dependent task,
then select the Predecessors tab. Enter the number of the predecessor and go
to the third column (Type). You will see a drop-down menu option and select
"Finish-to-Finish" as the constraint.

Using this, the second or dependent task finish date will follow along with
the actual finish date of the predecessor task.
 
W

WSB

MT_PMP

Thanks for the answer; I think this is what I needed. However, I can't
force the dependant taskes to shift, based on changes to the completion date
of the independant task though. It is possible that I have some other
setting not correct to allow for that?
 