Converting work days to calendar days

S

sushrutj

The MS Project 2007 file was created with work days. Now i want to
convert them to calendar days - how do i do this?

thanks.
 
M

Mike Glen

Hi sushrutj,

Welcome to this Microsoft Project newsgroup :)

Well... you can't. If you entered work into each task, Project
automatically calculates the Duration which is based on the calendar in use.
The Gantt chart then shows the task's duration on the calendar detailed in
Project/Project Information. Perhaps you'd give us an example of what you
have and then what you want.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top