Hadi said:
John,
I build this static master everymonth using the original subfiles. I
thought about copying the dates into the subfiles so I always have them but
this will add alot of overhead to the users file which they really do not
need to look at any of these fields.
Here is an example of what I have, this one of the projects I have (I only
show to Outlinelevel2). as you can see, each wbs summary task has its own
start and finish dates. the Construction(7) start field is what I want be
ablel to copy on a custom date field and i am just showing a sample here.
ideally, i'd like to have a column for Design(2) start & finish, Job
Estimate(4) start & finish and so on. the reason i need these columns is it
will help me in my sort functions. very often, i get a request to filter all
of the projects to show, for example, Project Name and only Design(2) and
Construction(7) underneath it. i then get asked to sort the list by
construction start date which is impossible to do unless i have a column that
show that and i then i can easily make my sort.
Construction Start Finish
(7) Start
Helms Install ID Gate Wiring 6/28/05 1/3/05 2/26/07
AJE Authorized(1) 6/28/05 1/3/05 2/16/05
Design(2) 6/28/05 2/16/05 6/28/05
Material ordered(3) 6/28/05 3/30/05 6/10/05
Job estimate(4) 6/28/05 3/31/05 5/12/05
Permits(5) 6/28/05 2/15/05 8/15/05
Construction Contract(6) 6/28/05 5/13/05 5/13/05
Construction(7) 6/28/05 6/28/05 11/30/06
I hope I am making it a little bit more clear
thanks
Hadi,
Sorry, it is not more clear. Unfortunately the more detailed example
only confused me more (it probably isn't showing up on my newsreader the
way you typed it in when you posted). I see no hierarchy and there
appears to be three columns of dates but I can't tell what they
represent. You mention only showing outline level 2 but I see a number
in parenthesis after each task name (?) and I have no idea what those
are. In other words, the whole thing got lost in translation.
You did mention a couple of other things however. First, if you could do
what you want by copying the dates into the user project files, why not
just do that? I don't see the "overhead" concern. There is no reason
this data should impact the users in any way and the only way they would
even see it is if they added those fields to the normal view they use.
Second, you mentioned that the reason you want to copy the dates is to
give you the necessary flexibility to do specific sorts. It isn't real
clear to me that any copied data is necessary to get the sorts you want.
Sorting can be combined with filtering and the Grouping feature can
often be used to develop specialized reporting. But until I can clearly
understand the hierarchy and file structure I can't say if any of these
approaches might work.
Tell you what, if you can e-mail me a coy of your Project file(s) and
fully explain what you want, maybe I can help you with a solution. If
the files have sensitive information, I can send you a macro that will
desensitize the files or you can download a similar macro from fellow
MVP, Jack Dahlgren's website at:
http://masamiki.com/project/macros.htm
Look for Jack's macro called "scrub".
John
Project MVP
jensenj6atatcomcastdotdotnet
(remove obvious redundancies)