Copy part of a project

J

Jim Patterson

I have a user who is requesting the steps necessary to accomplish the
following:
He is using Project 2000.

He has a project that he has split into two time frames- Jan-July 2006 and
July-Dec 2005. Both have been saved with a baseline.

He is wanting to copy the original July-Dec 2005 tasks and paste them below
the Jan-July 2006 tasks (these are yearly recurring tasks). The copy and
paste works, but it messes up his existing Gannt chart.

Thanks in Advance for any and all assistance,
 
J

Jim Patterson

Jan,

Thanks for the reply.
Good Question. I will go ask him and give you specifics as soon as
possible.--

Jim Patterson
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top