I have a "task" which is represented by a ship sailing from port a to
port b.
It will leave port a on 19/5/5. The voyage is 30 days. I would like
Project to display the length of the task "correctly". I have entered
duration in project as 30 days.
The task will take exactly 30 days it is not effort driven and the ship
will not arrive early or late. I have assumed the task will run every
hour of the day since the ship is always working as it is sailing from
a to b.
I have tried to use various settings in the calanders available in
project but cannot get it to display the proper end date - which is 30
"real" calander days after 19/5/5. Project seems to grossly over
estimate the end date.
Any help on how to get the correct end date would be appreciated.
port b.
It will leave port a on 19/5/5. The voyage is 30 days. I would like
Project to display the length of the task "correctly". I have entered
duration in project as 30 days.
The task will take exactly 30 days it is not effort driven and the ship
will not arrive early or late. I have assumed the task will run every
hour of the day since the ship is always working as it is sailing from
a to b.
I have tried to use various settings in the calanders available in
project but cannot get it to display the proper end date - which is 30
"real" calander days after 19/5/5. Project seems to grossly over
estimate the end date.
Any help on how to get the correct end date would be appreciated.