Cost accruel

E

Eva

Is it possible to input payment terms (advance payment, progress and
warranty) for tasks? Or must I set subtasks for these payments?

Thanks for reply. Eva
 
M

Mike Glen

Hi Eva,

Welcome to this Microsoft Project newsgroup :)

Well, Project is not an accounting program, so I would make a milestone for
each occasion and assign it the payment value in the Fixed Cost field.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
R

Rod Gill

Project is not a cost accounting product. I advise not doing this in Project
at all, rather output the relevant tasks and dates to Excel then track
partial payments etc there or in your accounting system.
 