Hi,
I want to prepare a cash flow. The project parameters are as follows:
Project Type: Construction (Interior fitout) of Retail Store.
Store Size: Approximately 5000 Sq.mtrs. distributed equally at 3 level
(Ground floor, First Floor, Second Floor)
Project Duration: approximately 100 days.
All the activities are outsourced to various contracting companies lik
Hvac, Electrical, fixturing, Carpentry, etc contractors.
All Cost of each activity is worked from a detailed BOQ which then sum
up to a contract value. For example, say: the contract value o
Electrical work is 1000 dollars.
My question is:
How Can I add the following payment terms for electrical contractor i
MSP?
Advance Payment before work start : 30%. Say, 300 dollars
Running bill Payments as the work progresses: 40%. Say, 400 dollars
Final bill payment after work completion: 30%. Say, 300 dollars.
I am struggling with:
Acrue at Start:allocates total cost at the start of the activity
Acrue at End: allocates total cost after completion of the activity
Acrue Prorated: allocates uniformly over the duration of the activity.
Is there any flexibility in MSP 2007 that can accomodate the paymen
terms as desired by me?
Please help.
Thanks and regards,
Navin D. Mistr
I want to prepare a cash flow. The project parameters are as follows:
Project Type: Construction (Interior fitout) of Retail Store.
Store Size: Approximately 5000 Sq.mtrs. distributed equally at 3 level
(Ground floor, First Floor, Second Floor)
Project Duration: approximately 100 days.
All the activities are outsourced to various contracting companies lik
Hvac, Electrical, fixturing, Carpentry, etc contractors.
All Cost of each activity is worked from a detailed BOQ which then sum
up to a contract value. For example, say: the contract value o
Electrical work is 1000 dollars.
My question is:
How Can I add the following payment terms for electrical contractor i
MSP?
Advance Payment before work start : 30%. Say, 300 dollars
Running bill Payments as the work progresses: 40%. Say, 400 dollars
Final bill payment after work completion: 30%. Say, 300 dollars.
I am struggling with:
Acrue at Start:allocates total cost at the start of the activity
Acrue at End: allocates total cost after completion of the activity
Acrue Prorated: allocates uniformly over the duration of the activity.
Is there any flexibility in MSP 2007 that can accomodate the paymen
terms as desired by me?
Please help.
Thanks and regards,
Navin D. Mistr