John Lissaman
I have a single construction activity and want to set up a standard S curve
cash flow acorss the duration. I also want to delay the actual cash flow to
be one month behind the actual construction dates.
Is this possible?
cash flow acorss the duration. I also want to delay the actual cash flow to
be one month behind the actual construction dates.
Is this possible?